Construction Update

February 2026

Structure Rising. Momentum Building.

February marked a major structural milestone at The Belvedere. Both buildings are now clearly vertical, with elevated slabs, columns, and garage levels taking shape week by week.

What was foundation work is now visible form.

Building 300 Progress
  • Level 1 elevated post tension slabs placed and stressed
  • Garage foundation walls completed
  • Columns extended to the second floor
  • Pool structure advanced with shell and beam framing underway
  • Crash walls and key structural elements installed at Level 1
  • Electrical and plumbing infrastructure integrated into slab pours

Second floor structural work is actively progressing, including pool level steel and cable placements. The building is no longer theoretical. It is dimensional and rising.

Building 301 Progress
  • Level 1 elevated slab placements completed across multiple pours
  • Post tension cable stressing, cutting, and grouting finalized on early sections
  • Foundation walls completed and backfilled
  • Underground plumbing installed in slab on grade areas
  • Level 2 formwork and decking initiated

With Level 1 established and Level 2 underway, the building mass is beginning to define itself from the street and rail corridor.

Civil & Infrastructure Work
  • Utility water line extension underway along Paul Street
  • Coordination and water line work beneath the Union Pacific rail line progressed
  • Storm infrastructure and retaining elements installed
  • Environmental inspections and compliance maintained

These systems support long term performance and delivery readiness.

On Site Activity

Crew presence increased throughout the month as structural trades accelerated. Concrete, steel, plumbing, and electrical teams are sequencing efficiently, allowing pours, stressing, and follow up trades to move continuously.

Safety oversight and environmental inspections remained consistent across all phases.

What This Means for Buyers

February moved The Belvedere firmly into vertical construction.

Elevated decks are complete across multiple levels. Columns are rising. The pool structure is taking shape. Utilities are embedded into permanent structure. The building footprint is clearly defined and upward progress is visible each week.

As structural levels advance, future phases including façade systems, glazing, and interior framing move closer on the timeline.

The Belvedere remains on schedule toward Fall 2027 delivery.

January 2026

Progress On Site

As we enter the new year, construction at The Belvedere is moving forward smoothly and on schedule.

Structural work is progressing across both buildings, with post-tension decks placed successfully and additional pours scheduled in the coming weeks. Materials continue to arrive on site ahead of future phases, and coordination between trades remains strong.

Quality assurance is a priority. Our structural engineering team has been invited on site as part of ongoing review, and aerial documentation continues throughout construction. Site civil and utility work is also advancing in alignment with design plans.

We are pleased to share that pool deck is underway, marking another visible milestone on site.

The project is active and evolving daily, and we appreciate the care and precision that goes into each step. Additional updates will be shared monthly.

Thank you for your continued interest in The Belvedere.

Recent

Categories