March 2026
Construction continues to move steadily with both buildings advancing vertically and major structural work now well underway.
Level 2 activity has been a primary focus. At Building 301, multiple slab pours have been completed, including the first Level 2 placement, with additional pours following close behind. Building 300 has progressed through ground-level slab work and pool wall construction, with Level 2 structural work now actively underway.
All ground floor slabs across both buildings have now been poured, marking a key milestone as the project transitions fully into elevated structure. Formwork and decking are in place and continuing upward, with framing and structural progression beginning toward Level 3.
Coordination across trades remains active and ongoing. This includes early integration of mechanical, electrical, and plumbing systems, along with conduit, floor boxes, and structural elements that need to be embedded ahead of future pours. Exterior coordination has also begun, including balcony systems, storefront assemblies, and masonry anchoring.
Off-site and infrastructure work continues in parallel. Utility work under the rail line has been completed, and installation of Austin Energy vaults is now underway, reflecting updates to the original plan. These systems will support long-term building operations and are being integrated alongside ongoing site work.
The façade is beginning to take shape through mockups and material testing. Moisture barrier application is in progress, setting up the next phase of exterior installation, including panels and masonry.
What's Next
- Continued Level 2 slab pours across both buildings
- Progression into Level 3 structure
- Ongoing MEP integration ahead of elevated pours
- Expansion of exterior façade work following mockup validation
February 2026
Structure Rising. Momentum Building.
February marked a major structural milestone at The Belvedere. Both buildings are now clearly vertical, with elevated slabs, columns, and garage levels taking shape week by week.
What was foundation work is now visible form.
Building 300 Progress
- Level 1 elevated post tension slabs placed and stressed
- Garage foundation walls completed
- Columns extended to the second floor
- Pool structure advanced with shell and beam framing underway
- Crash walls and key structural elements installed at Level 1
- Electrical and plumbing infrastructure integrated into slab pours
Second floor structural work is actively progressing, including pool level steel and cable placements. The building is no longer theoretical. It is dimensional and rising.
Building 301 Progress
- Level 1 elevated slab placements completed across multiple pours
- Post tension cable stressing, cutting, and grouting finalized on early sections
- Foundation walls completed and backfilled
- Underground plumbing installed in slab on grade areas
- Level 2 formwork and decking initiated
With Level 1 established and Level 2 underway, the building mass is beginning to define itself from the street and rail corridor.
Civil & Infrastructure Work
- Utility water line extension underway along Paul Street
- Coordination and water line work beneath the Union Pacific rail line progressed
- Storm infrastructure and retaining elements installed
- Environmental inspections and compliance maintained
These systems support long term performance and delivery readiness.
On Site Activity
Crew presence increased throughout the month as structural trades accelerated. Concrete, steel, plumbing, and electrical teams are sequencing efficiently, allowing pours, stressing, and follow up trades to move continuously.
Safety oversight and environmental inspections remained consistent across all phases.
What This Means for Buyers
February moved The Belvedere firmly into vertical construction.
Elevated decks are complete across multiple levels. Columns are rising. The pool structure is taking shape. Utilities are embedded into permanent structure. The building footprint is clearly defined and upward progress is visible each week.
As structural levels advance, future phases including façade systems, glazing, and interior framing move closer on the timeline.
The Belvedere remains on schedule toward Fall 2027 delivery.
January 2026
Progress On Site
As we enter the new year, construction at The Belvedere is moving forward smoothly and on schedule.
Structural work is progressing across both buildings, with post-tension decks placed successfully and additional pours scheduled in the coming weeks. Materials continue to arrive on site ahead of future phases, and coordination between trades remains strong.
Quality assurance is a priority. Our structural engineering team has been invited on site as part of ongoing review, and aerial documentation continues throughout construction. Site civil and utility work is also advancing in alignment with design plans.
We are pleased to share that pool deck is underway, marking another visible milestone on site.
The project is active and evolving daily, and we appreciate the care and precision that goes into each step. Additional updates will be shared monthly.